What to Check Before Leasing an Industrial Building in Mexico

Last updated: November 2026. By the Mexecution team.
Summary
Before leasing an industrial building in Mexico, verify ten things in writing:
- The owner and the signatory’s authority to sign.
- That your intended use is permitted and has an approval route.
- Deliverable electrical capacity for your unit and load.
- Water supply and wastewater discharge.
- Building condition, from an independent inspection.
- Fire protection for your process and storage.
- Truck and employee access.
- The full occupancy cost, not just the rent.
- Delivery, handover and when rent starts.
- Exit obligations: restoration, assignment and termination.
Use the checklist below to organize the evidence, then turn any open item into a clear condition before you sign.
What operation must the building support?
Write a short operating brief before reviewing the landlord's specifications, because your team needs a consistent definition of an acceptable facility. Include the production process or warehouse function, equipment list, staffing by shift, inbound and outbound movements, storage method, expected opening date and expansion needs, with a named internal owner for each requirement.
Separate requirements that would disqualify a property from preferences that could be traded against cost or convenience. For example, your process engineer might require a particular electrical configuration while your commercial team merely prefers an additional office area; the evaluation should make that distinction explicit rather than giving both items equal status in a spreadsheet.
Ask the project team to sign off this brief before inspections begin. If the requirement later changes, record the reason and revisit the affected properties, so that an attractive building does not quietly redefine the business case. For the earlier stage of the search, use our industrial site selection guide.
What evidence should you request before leasing?
Use the following table as an evidence request, adapting the specialist responsibilities to your project. A missing document should remain an open item until someone has established whether it is necessary and obtained an acceptable answer.
| Check | Evidence to request | Decision before commitment |
|---|---|---|
| Owner and signing authority | Ownership documents and authority of the proposed signatory | Counsel confirms the correct contracting parties |
| Intended use | Written description of the process and relevant use or operating documentation | Confirm that the proposed activity has an identified approval route |
| Electricity | Load schedule, connection documents and engineer review | Confirm capacity, works, responsibilities and energization conditions |
| Water and discharge | Proposed supply arrangement, demand profile and discharge assessment | Confirm an acceptable operating solution |
| Building condition | Independent inspection and relevant tests | Price or resolve defects and suitability gaps |
| Fire protection | Process and storage layout reviewed by the appropriate specialists | Identify required changes and acceptance criteria |
| Logistics | Truck movement plan and route checks | Demonstrate access for the intended vehicles and schedule |
| Occupancy cost | Comparable landlord offer and priced tenant works | Approve the full cash requirement |
| Delivery and handover | Agreed specification and acceptance procedure | Define when possession and payment obligations begin |
| Exit obligations | Proposed restoration, assignment and termination terms | Understand the consequences of the operating plan changing |
Who owns the property, and who can sign the lease?
Ask Mexican counsel to reconcile the property description in the draft lease with the documents supplied by the owner, including the unit boundaries, shared areas, parking, loading areas and any land reserved for expansion. Obtain a clear explanation of who has authority to grant the lease and who will remain responsible for the obligations attributed to the landlord.
Where a property sits inside a larger development, ask for the park rules and the documents governing shared infrastructure. Review whether access, security, maintenance and service charges are controlled by the same party that is signing the lease, and request the appropriate commitments from each responsible entity rather than assuming one signature covers everything.
Give counsel your proposed alterations and operating activities at the beginning of the review. Ask them to distinguish permissions already documented from applications still required, and to identify any conditions that should be resolved before the lease becomes unconditional.
Is there enough electricity for your equipment?
Industrial supply at medium and high voltage goes through a formal procedure with CFE, listed on the government’s energy procedures portal. [1] Get project-specific confirmation of the connection arrangement before treating electricity as done.
Ask your electrical engineer to reconcile the installed equipment, documented supply arrangement and proposed operating load, including startup demand, operating hours and any planned expansion. Request a written list of additional works, approvals and tests, with a responsible party and an estimated completion basis for each item.
When a listing says that power is available, ask what that statement refers to: existing infrastructure, an approved connection, a proposed upgrade or a service already operating under a particular arrangement. Keep the answer alongside the supporting documents and specify which evidence your engineer needs before accepting the building for the intended operation.
Agree what happens if the required service is not ready when the building is physically complete. The commercial negotiation should address the consequences for access, installation, rent commencement and any agreed contingency, with wording prepared for the actual transaction rather than copied from a generic checklist.
How do you check water supply and discharge?
CONAGUA's information portal links to REPDA records covering national-water concessions and allocations, as well as discharge permits. [2] Treat those records as one source of evidence where relevant, then ask the appropriate specialist to establish how the proposed facility will receive water and manage its own discharge.
Prepare separate requirements for domestic use, production, cooling, cleaning and fire protection, using the quantities and quality criteria specified by the process designers. Ask the landlord or park operator to document what is included in the offer, how it is measured, and which upgrades or operating controls would remain your responsibility.
For a process that generates wastewater, provide an expected discharge profile for specialist review rather than accepting a general statement that drainage exists. Request an explanation of the proposed destination, treatment arrangements, applicable approvals and monitoring responsibilities, including the consequences of changing the production process later.
What should a building inspection cover?
RICS describes technical due diligence as a systematic investigation and professional assessment of a property's physical characteristics, intended to inform a prospective purchaser, occupier or financier about technical risks. [3] Your appointment should specify what will actually be inspected, tested and reported, because a building tour alone is not the inspection scope you are purchasing.
Ask the relevant specialists to assess the roof, drainage, structure, floor, loading facilities and building services against your proposed layout, with access to drawings and maintenance records where available. Identify which conclusions rely on documents, which rely on visual observation and which require further testing, then record those limitations in the decision file.
Have the process and structural engineers review concentrated equipment loads, racking and any proposed penetrations or suspended services. Instead of relying on a generic description such as “manufacturing ready,” ask them to state whether the proposed installation is acceptable, what work is required and which assumptions still need verification.
For fire protection, give the reviewer the actual product, packaging, storage height and process information. Request a written assessment of the proposed arrangement and the relevant authority, insurer or customer requirements, with a priced path to any necessary changes.
Can trucks and employees reach the building easily?
Walk the journey from the public road to the unloading position with the logistics team, checking the proposed vehicle dimensions, gate process, queuing space, turning movements and separation from pedestrians. Test the route at the times your operation expects to receive goods, rather than relying only on an appointment arranged for a quiet inspection period.
Ask carriers to quote the actual origin and destination lanes, including the service assumptions behind their prices and transit estimates. If the plan includes cross-border shipments, ask the logistics and customs advisers to model the complete movement through the selected crossing, with an agreed response to disruption.
Review shift transport and staff access in the same practical way. Request a proposed pickup area, transport plan and access arrangement for employees and contractors, then ask HR and operations to confirm that these assumptions support the intended hiring and shift pattern.
What does the lease really cost?
Create one cost model for every shortlisted building, using the same currency, area basis, lease duration and operating assumptions. Include quoted rent, stated adjustments, deposits, guarantees, park charges, insurance allocations, fit-out, utility works and the professional work needed to bring the facility into operation, leaving uncertain items visible rather than replacing them with zero.
Separate refundable cash commitments from expenses and distinguish one-time works from recurring charges. Ask finance to decide how taxes, exchange rates and recoverable amounts should appear in the investment model, then show both the initial funding requirement and the recurring operating view.
Test a delayed-opening scenario and a slower growth scenario. The purpose is to show whether the proposal remains acceptable if the operation needs more time or less space than initially expected.
How do you turn landlord promises into enforceable terms?
Use a responsibility schedule that assigns each improvement, approval, inspection and handover document to a named party. Link the schedule to the agreed drawings and specifications, and ask counsel to reflect the appropriate milestones and remedies in the transaction documents.
Distinguish permission to enter the building, permission to install equipment, acceptance of landlord works and readiness to operate. Define what each milestone requires, who confirms it and how unresolved defects will be handled, so that the project team is not using one word such as “delivery” for several different events.
Ask for a documented handover inspection, a list of incomplete items and a process for closing them. Review warranties, maintenance responsibilities and the condition expected when the lease ends, including the treatment of tenant-installed equipment and modifications.
How do you make the final decision?
For each unresolved item, record the evidence missing, the person responsible, the next action and the consequence if it is not resolved. Classify the item as a condition that must be met, a cost the business has accepted or a risk that still needs a decision, with the approval of the person authorized to make that trade-off.
Use three outcomes for the property review: proceed on agreed conditions, continue investigation or reject. This simple decision structure helps the team avoid presenting a building as fully approved while critical engineering or legal questions are still open.
If you need help selecting the advisers who will support the work, our guide to choosing an industrial real estate advisor sets out questions to use when defining the engagement.
Frequently asked questions
What documents should we request first?
Begin with the property identification, draft commercial offer, available ownership and authority documents, drawings, utility information and maintenance records, then let your legal and technical teams tailor the request to the operation. The goal is a usable decision file, not a large folder with no clear review responsibility.
Can we rely on the capacity shown in a property listing?
No. Treat it as a screening statement and ask your engineer to verify what it means for your load and supply arrangement, including whether you need a new service or a change to the existing one.
Does every project need the same environmental approval?
No. SEMARNAT lists several environmental-impact procedures, including particular and regional assessments, project modifications and requests concerning exemption or non-requirement. [4] Ask a qualified adviser to determine the applicable federal, state and local pathway for your activity, rather than treating a single form as universal permission to operate.
Should we choose the building with the lowest asking rent?
Not automatically. Compare it using the same complete cost and readiness model as the alternatives, then decide whether its fit-out, service arrangements, delivery conditions and operating suitability meet the business case. A lower rent is a useful input, but your approval should cover the whole proposed commitment.
How can Mexecution help before you lease?
Mexecution is a Mexico industrial real estate marketplace and site-selection advisor for foreign manufacturers. Its About Us page reports a network of 300+ industrial parks, 80+ developers, 20+ international and local brokers and 80+ C-level service providers, and says it delivers 5 to 10+ tailored location options within 48 hours.
Contact Mexecution with your operating brief, preferred location, space requirement and target opening date, together with the technical or commercial questions still unresolved. Ask for a clearly scoped next step that identifies the evidence needed before your team commits to a building.
Sources
[1] Government of Mexico. Energy procedures portal: industrial medium- and high-voltage supply.
[2] CONAGUA. Water information systems portal. Source for the scope of REPDA and other water information tools.
[3] RICS. Technical due diligence of commercial property. Professional technical-due-diligence framework; not Mexican law.
[4] SEMARNAT. Environmental impact procedures. Source for the listed federal procedure categories, not a project-specific approval decision.